- Leveling the Total Station must be accomplished to sufficient accuracy otherwise the instrument will not report results
- Leveling the instrument takes 30 to 45 minutes make sure you can see all targets from the instrument station before going through the process
Step 1: Tripod Setup
Step 2: Mount Instrument on Tripod
- Place Instrumenton Tripod
- Secure withcentering screwwhile bracing theinstrument withthe other hand
- Insert battery ininstrument beforeleveling
Step 3: Focus on Survey Point
Focus the optical plummet on the survey point
Step 4: Leveling the Instrument
- Adjust the leveling foot screws to center the
survey point in the optical plummet reticle
- Center the bubble in the circular level by
adjusting the tripod legs
- Loosen the horizontal clamp and turn instrument until plate level is parallel to 2 of the leveling foot screws
- Center the bubble using the leveling screws- the bubble moves toward the screw that is turned clockwise
- Rotate the instrument 90 degrees and level using the3rd leveling screw
- Observe the survey point in the optical plummet and center the point by loosening the centering screw and sliding the entire instrument
- After re-tightening the centering screw check to make sure the plate level bubble is level in several directions