How to Leveling the Total Station


  • Leveling the Total Station must be accomplished to sufficient accuracy otherwise the instrument will not report results
  • Leveling the instrument takes 30 to 45 minutes  make sure you can see all targets from the instrument station before going through the process
Step 1: Tripod Setup





  • Tripod legs should be equally spaced





  • Tripod head should be approximately level





  • Head should be directly over survey point






  • Step 2: Mount Instrument on Tripod

    • Place Instrument 
      on Tripod
    • Secure with 
      centering screw 
      while bracing the 
      instrument with 
      the other hand
    • Insert battery in 
      instrument before 
      leveling



    Step 3: Focus on Survey Point

    Focus the optical plummet on the survey point



    Step 4: Leveling the Instrument
    •  Adjust the leveling foot screws to center the
    survey point in the optical plummet reticle
    • Center the bubble in the circular level by
    adjusting the tripod legs

    • Loosen the horizontal clamp and turn instrument until plate level is parallel to 2 of the leveling foot screws
    •  Center the bubble using the leveling screws- the bubble moves toward the screw that is turned clockwise
    • Rotate the instrument 90 degrees and level using the3rd leveling screw
    • Observe the survey point in the optical plummet and center the point by loosening the centering screw and sliding the entire instrument
    •  After re-tightening the centering screw check to make sure the plate level bubble is level in several directions